Do not run a tensioned green wall cable across a building movement joint without a designed movement detail. The cable can create an unintended connection between sections that are meant to move independently. Keep the building’s movement strategy visible in the planting and hardware drawings.
This coordination note is for facade and landscape teams procuring green wall cable hardware. It explains what belongs in the interface schedule before a supplier is asked to price cable lengths and brackets.
Identify the joint before drawing the grid
Ask the building designer to mark the joint and the movement envelope relevant to the support system. A line shown on an elevation may represent more than a cosmetic break. Determine which structural zones each fixing belongs to.
The Jakob GreenSolutions catalogue and architectural cable catalogue provide useful component context. They are not a project-specific movement-joint design. The important procurement question is whether the proposed arrangement preserves the required separation throughout the relevant movement.
Divide the system into identifiable zones
Independent cable sections can make responsibilities easier to define, but their end supports still require design. Do not assume that leaving a visible gap automatically resolves all loads or maintenance issues. Our green wall cable load guide explains the need to consider mature planting and the supporting arrangement.
| Drawing item | Information to record |
|---|---|
| Building joint | Location and designer-defined movement requirement |
| Fixing zone | Structural section supporting each bracket |
| Cable section | Unique ID and termination locations |
| Planting interface | Training and pruning responsibilities |
Catalogue illustration: Slotted Adjustable Cable Support — Matte silver appearance. Shown as a component reference, not an installation drawing or test result.
For anchor selection, use the relevant manufacturer data, such as the Hilti technical guide library, with the project substrate and design. Neither a strong bracket nor a larger anchor makes it appropriate to restrain a movement joint unintentionally.
Do not confuse tension adjustment with movement capacity
A turnbuckle’s adjustment range is used for a defined assembly purpose. It should not be assumed to provide free movement after the cable has been set and locked. Ask the responsible designer how the joint is accommodated, then identify the exact components implementing that detail.
If the installation is phased, use our phased cable kit guide to keep zone boundaries and drawing revisions aligned. Label temporary conditions separately from the final arrangement. This helps avoid a later installer adding a continuous cable because an earlier section appears unfinished.
Catalogue illustration: Female Threaded Standoff Foot — Matte silver appearance. Shown as a component reference, not an installation drawing or test result.
Include the planting team in the interface review
Vegetation can bridge a gap even where the hardware remains separate. Coordinate training and pruning so the planting does not defeat the maintenance strategy. RHS climber information and tying-in guidance are horticultural references that help the landscape team frame those decisions.
Define access to both sides of the interface. Our repairable cable section guide covers replacement planning. A section that can be inspected and replaced independently is easier to manage than one whose fittings disappear behind mature planting and inaccessible services.
Turn coordination into a clear order
Submit the elevation, sections and zone schedule through OEM/ODM development. Ask the supplier to identify included components without claiming responsibility for building movement unless that service is explicitly agreed. Review the appropriate manufacturing capabilities for special brackets or fabrication.
Specify exposure and finish for each zone. IMOA coastal guidance provides background where salts are relevant; protected locations can still collect deposits. Keep maintenance instructions with the delivered kit.
During drawing review, colour-code the two structural zones and trace every cable and bracket back to its support. This coordination exercise can expose an accidental cross-connection before fabrication. Keep that marked drawing with the release package so later substitutions are checked against the same intended separation.
Catalogue illustration: Rectangular Threaded Mounting Plate — Polished silver appearance. Shown as a component reference, not an installation drawing or test result.
The NIST conformity assessment overview distinguishes inspection and testing from certification. Use that distinction in submittals: a dimensional check of a bracket does not verify the building movement detail. GS1 traceability principles can help connect section IDs, drawings and supplied batches.
Frequently asked questions
Can we simply loosen a cable beside the joint? Not as a substitute for a designed detail. The resulting geometry and loads need review.
Must every section use different hardware? No. Repeated parts may be suitable, but their locations and responsibilities should remain identifiable.
What is the minimum RFQ package? The joint location, movement information from the designer, fixing zones, planting layout and quantities. Send the coordinated drawings before releasing cable lengths. That makes the intended separation explicit and reduces the risk of an unintended connection being introduced during installation.